Group Four project in Bkassine, Chouf, at shell stage before interior fit-out works begin
Fit-Out

Fit-Out Works in Lebanon

Office, residential, retail and commercial fit-out: partitions, ceilings, flooring, joinery coordination and final finishes.

Inside The Shell

Working to somebody else structure

Fit-out is constrained work. The shell is already built, the slab levels are what they are, and the risers land where the base build put them. The job is to deliver the tenant drawings inside those constraints without pretending the constraints are not there.

Most fit-out overruns come from the ceiling void. Ducts, trays, sprinklers, and lighting all want the same 300mm, and the conflict only becomes obvious when the second trade arrives. We coordinate that space before the first bracket goes up.

Scope of works

01

Strip-Out & Preparation

Clearing back to the shell, protecting what stays, and confirming the levels and services you have actually inherited.

  • Strip-out and waste removal
  • Protection of retained elements
  • Level and services verification
02

Partitions & Ceilings

Drywall partitions and suspended ceilings set out from the tenant drawings and coordinated with the void above.

  • Drywall and glazed partitions
  • Suspended and gypsum ceilings
  • Ceiling void coordination
03

Flooring & Finishes

Screeds, raised floors, and final floor finishes laid to the levels the joinery and doors depend on.

  • Screeds and levelling
  • Raised access floors
  • Final floor finishes
04

Joinery Coordination

Built-in joinery surveyed against the constructed dimensions rather than the drawing, then installed and adjusted.

  • Site survey before fabrication
  • Installation and adjustment
  • Ironmongery and door sets
05

Lighting & Handover

Lighting preparation, second fix, snagging, and the handover pack the tenant needs on day one.

  • Lighting preparation and second fix
  • Snagging and defect close-out
  • Handover and as-built records

On site

Concrete shell at a Group Four project in Bkassine, Chouf, before interior fit-out begins
Shell handed over, levels and risers confirmed before fit-out.
Group Four design visualisation of a terrace and covered outdoor living space with stone and timber finishes in Lebanon
Design stage: finishes and fixed joinery set out before anything is ordered.
Finished paving, balustrades and terraces at a Group Four project in Lebanon
Final finishes at handover stage.

Featured Projects

A selection of our recent work demonstrating precision craftsmanship and architectural excellence across the Chouf, Mount Lebanon, and Beirut.

Ready to Build Your Next Project?

With over 20 years of combined experience across Beirut, the Chouf, and Mount Lebanon, our engineering firm has the expertise to bring your vision to life. Let's create something extraordinary together.

Let's Discuss Your Project

Our team is based in Baakleen, Chouf, and works with clients across Beirut, Mount Lebanon, and beyond. Reach out for a free consultation — we'd love to hear about your project.

Office Location

Rabih Fares Center, Baakleen, Chouf 1509, Lebanon

View on Map

Phone

+961 71 111 755

Chat on WhatsApp

Email

[email protected]

We typically respond within 24 hours

Follow Our Work

Send Us a Message

Fit-out across Beirut and Mount Lebanon

Fit-out runs to tighter programmes than new build, often around a tenant handover date. Being close enough to attend daily is what keeps those dates realistic.